Future Plans

This section provides a brief description of the Winfrith site as outlined in the NDA's strategy.

The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.


Site End States

 Current plans are for the site to be decommissioned, cleared and delicensed.

Current Key Milestones

 Year

Milestones 

 2007  Complete decommissioning of active handling building
 2009  Complete remediation of B2/B3 complex
 2012  Complete decommissioning of Dragon reactor complex
 2014  Complete decommissioning of on-site effluent systems and sea tanks
 2017  Complete decommissioning of steam generating heavy water reactor (SGHWR) complex
 2020  Final site clearance and closure