Future Plans

This section provides a brief description of the Trawsfynydd site as outlined in the NDA's strategy.

The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.


Site End States

Current plans are to delicense the site for reuse in future recreational purposes to reflect its location within the Snowdonia National Park.

Current Key Issues

 Year

 Milestones

 2007  Completion of ILW store for storage of processed operational waste
 2011  Demolition of ponds complex
 2012  Enter care and maintenance
 2040  Packaged ILW transported to repository
 2046  Demolition of waste store in line with local planning permissions and public enquiry findings
 2088  Start of final site clearance
 2096  Final site clearance and closure