Future Plans

This section provides a brief description of the Springfields site as outlined in the NDA's strategy.

The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.


Site End States

Current plans are for the site to be delicensed for unrestricted reuse by March 2031, in line with perceived stakeholder expectations and to provide a prudent assumption on which to base decommissioning estimates and their associated financial provision.

Current Key Milestones

 Year

Milestones 

 2006 Magnox uranium plan production operations cease
 2007 Magnox Metal and fuel assembly plants close - production operations cease and Post Operations Clean Out(POCO) starts
 2008 Magnox decommissioning programme starts
 2008 Natural residue recovery plant ceases operation and POCO starts. Recovery of enriched residue "backlog" completed
 2009 Enriched residue plant ceases operation and POCO starts
 2010 Magnox fuel assembly plant final decommissioning complete
 2011 Enriched residue recovery plant final decommissioning complete
 2012 Magnox metal and rod plants final decommissioning complete
 2016 Hex/Kiln plant production operations cease and POCO starts
 2020 Hex/Kiln plant final decommissioning complete
 2023 Oxide fuel production operations cease and POCO starts
 2028 Oxide fuel complex final decommissioning complete
 2031 Assumed site end point - final site clearance and ground remediation