Future Plans

Location

Hinkley Location

Performance Updates

Find out more about Hinkley Point A's Performance, visit our Programme Performance Updates section.

See also

NDA Strategy Document

NDA Strategy Document

After extensive consultation with our stakeholders, Government approved our Strategy published on 30 March 2006

NDA Strategy (pdf)

Find more documents in our comprehensive Document Library.

.
Home > Our Sites > Hinkley Point A > Future Plans  

Future Plans

This section provides a brief description of the Hinkley Point site as outlined in the NDA's strategy.

The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.


Site End State

 Current plans are for the site to be delicensed.


  Current Key Milestones
Year    Milestones

2012

 Complete decommissioning and backfill of Turbine Hall
  2013  Complete decommissioning of Magnox vault
  2016  Complete processing of historic ILW
  2017  Start of safestore care & maintenance
  2095  Reactor buildings decommissioning complete
  2104  Final site clearance and closure