Forthcoming Events

10 December 2009
Socio Economic Panel
Panel to consider funding requests under £100,000.

27 October 2009
Socio Economic Panel
Panel to consider funding requests under £100,000.

10 September 2009
Socio Economic Panel
Panel to consider funding requests under £100,000.

Press Enquiries

For urgent enquiries out of office hours, please use the mobile phone numbers below:

Bill Hamilton
Head of Communications

Office: 01925 802193
Mobile: 07816 315132

Brian Hough
Communications Manager

 Office: 01925 802177
Mobile: 07812 554009

Richard Flynn
Communications Manager

Office: 01925 802075
Mobile: 07812 553965

Related Documents

Web Updates

Keep informed with the latest news and developments from the NDA

Latest News

21 June 2007
Response to Independent on Sunday
Letter to newspaper related to Government's consultation on advance fuel allocation.

14 June 2007
Advance Allocation Consultation
DTI launches public consultation into advance allocation of THORP reprocessing products to overseas customers in certain circumstances.

10 January 2007
NDA Response to HSE Statement on THORP Re-start
Health and Safety Executive grants consent for the re-start of THORP.

18 September 2006
NDA Review of SMP
NDA provides a report reviewing progress over the past year and considers future potential strategic role of Sellafield Mox Plant (SMP).

02 March 2006
THORP Update
Revised assessment of issues associated with non-restart and restart options for THORP, Sellafield.

Find more News Items

.


.
Home > News and Events > Latest NDA Statement on THORP  

Latest NDA Statement on THORP - 16 November 2005

16 November 2005

Approximately 50% of the NDA’s annual budget of £2.2bn is derived from income from various commercial activities. Of this, more than a half comes from the storage and reprocessing of spent nuclear fuel at the THORP plant.

As outlined in the NDA Draft Strategy, published in August, the total projected revenue from THORP from now until 2010, when current orders are scheduled for completion, is £5.1bn.

Planned income from storage and reprocessing activities at THORP for this financial year was £575m. However, the actual financial impact of the outage will be mitigated by a number of factors:

  • The nature of the contracts with THORP’s customers are such that certain planned payments continue to be made. 
  • A seven-week planned outage was timetabled and accounted for.
  • Staff have been redeployed to other decommissioning duties.
  • The NDA has insurance cover including material damage and business interruption which covers incidents of this nature.

We must wait until the NII has published its report into the incident and we have had the opportunity to understand the implications of its findings before a clear way forward for THORP is determined. In the meantime safety remains the NDA’s number one priority and we are working closely with British Nuclear Group to scrutinise potential engineering solutions for a possible restart. The cost of any restart solution has not yet been fixed.

Because of these factors our current estimate is that planned revenue from THORP will be reduced by around 5% for the full financial year 05/06 due to the plant’s outage. In the event of a restart of reprocessing operations much of the lost income may be recovered from customers over time and the final quantification will depend on the engineering solution.

If all regulatory issues are addressed and a restart is made by Summer 2006, then we expect that contractual commitments can be achieved by the end of 2010.